NEW QUESTION 103
Your customer wants to add certain values from a source document into the account document automatically.
You recommend them to use a function module.
Which of the following are attributes of function modules? (Choose two.)
- A. Function modules are reusable subroutines.
- B. Function modules can be called out of ABAP programs.
- C. Function modules have to be released by SAP.
- D. Function modules are automatically imported via Support Packages.
Answer: A,B
NEW QUESTION 104
A company wants to use Profitability Analysis (CO-PA) to obtain an early analysis of their anticipated profits. Which functionality provides the best results?
- A. Transfer sales orders and quotations from SD to costing-based CO-PA and use record type "A" for analysis.
- B. Transfer sales orders and quotations from SD to account-based CO-PA and use record type "F" for analysis.
- C. Transfer the plan balance data from Fl to account-based CO-PA and use record type "F" for analysis.
- D. Analyze sales quotation as a detail value.
- E. Transfer the plan data from the "Sales and operation planning" to costing-based CO-PA and use record type "P" for analysis.
Answer: A
NEW QUESTION 105
Which of the following views and results do profit center accounting reports in New GL provide? (Choose three.)
- A. Return on investment
- B. Fixed and variable cost portions
- C. Cost of goods sold
- D. Variance categories of production
- E. Balance sheet statement
Answer: A,C,E
NEW QUESTION 106
A controlling area has been created for more than one company code. Which of the following statement are not correct?
Please choose the correct answer.
Response:
- A. The profit centre covers more than one company codes.
- B. The closing in management accounting is independent of final closing in financial accounting.
- C. The operating chart of accounts for company codes & controlling area has to be identical.
- D. Group costing is required for goods manufactured across the company code.
Answer: B
NEW QUESTION 107
Which of the following are interactive functions available in the SAP List Viewer There are 3 correct answers to this question.
- A. Dual control.
- B. Sorting.
- C. Master data modification.
- D. D Filters.
- E. Summation.
Answer: B,D,E
NEW QUESTION 108
What is the basis for creating projects in SAP Solution Manager?
- A. Business scenarios
- B. Business documentation
- C. Business content
- D. Business blueprint
Answer: A
NEW QUESTION 109
Your customer wants to see a P&L statement for profit centers by the cost-of-salesaccounting approach. Which of the following is the minimum requirement?
- A. Activate profitability analysis.
- B. Create a derivation rule for the functional area.
- C. Activate the scenario functional area in New GL.
- D. Enter the functional area in the profit center master.
Answer: C
NEW QUESTION 110
When creating an internal order, which data is derived from the order type?
There are 2 correct answers to this question.
Response:
- A. Commitment profile
- B. Model or reference order default entries
- C. Settlement profile
- D. Settlement rule
Answer: B,C
NEW QUESTION 111
What is a report group in Report Painter required for?
- A. To add a report as a sub folder in the Easy Access Menu.
- B. To assign further reports via the report/report interface.
- C. To run reports in costing based profitability analysis.
- D. To serve as a template for the creation of new Report Painter reports.
Answer: B
NEW QUESTION 112
What is the name of the infrastructure that supports core business solutions in four subcomponents including people integration, information integration, process integration, and application platform?
- A. SAP Exchange Infrastructure
- B. SAP Web AS
- C. SAP NetWeaver
- D. SAP Business Process Management
Answer: C
NEW QUESTION 113
Which are the main elements of the Roadmap structure screen?
- A. Roadmap structure Blueprint area Go-live Area
- B. Roadmap structure Viewing/Text area Go-live Area
- C. Roadmap structure Blueprint area Attachments Area
- D. Roadmap structure Viewing/Text area Attachments Area
Answer: D
NEW QUESTION 114
Select the benefits of SAP Solution Manager from the list of items below. (Choose three)
- A. Separation of SAP solutions
- B. Integration of SAP Solutions
- C. Faster ROI
- D. Lower ROI
- E. Reduced cost of operations
Answer: B,C,E
NEW QUESTION 115
How can you separate vendor payments for construction advances from regular down payments?
- A. Make regular down payments, open them for update, and flag them as down payments.
- B. Create and use a Special General Ledger indicator for construction advances.
- C. Configure a new vendor account group and assign construction advance vendors to it.
- D. Perform a separate payment run for payment of construction advances.
Answer: B
NEW QUESTION 116
An Automotive customer works with 600,000 material numbers in a multi-level production environment. The whole costing run takes several hours. Now they are simulating the impact of an alternative production setup, which uses the same raw materials and semi-finished products.
What option would you recommend to significantly shorten the duration of the costing run?
- A. Assign a suitable transfer control strategy to the relevant costing variant in the IMG
- B. Use the Schedule Manager to optimize the duration of the Costing Run.
- C. Use the easy cost planning function for simplified and accelerated costing.
- D. Define a mixed costing strategy and maintain mixing ratios.
Answer: A
NEW QUESTION 117
Which objects can be assigned to an asset master record? There are 3 correct answers to this question.
- A. Cost center
- B. WBS element.
- C. Internal order.
- D. Profitability segment.
- E. Profit center.
Answer: A,B,C
NEW QUESTION 118
Your New GL customer uses real-time reconciliation of CO and FI. The customer wants to show the value flow of activity allocations between cost centers assigned to different profit centers. What does the customer have to configure? (Choose two)
- A. Select profit center as a characteristic for real time reconciliation between CO and FI.
- B. Define a G/L reconciliation account for direct activity allocation.
- C. Carry out a reconciliation run for activities types in the new GL.
- D. Execute the periodic transfer to profit center accounting.
Answer: A,B
NEW QUESTION 119
What is the main idea of SAP NetWeaver Information Lifecycle Management (ILM)?
- A. ILM is the new tool to archive SAP NetWeaver Business Warehouse objects.
- B. ILM replaces data archiving.
- C. ILM is an external storage system delivered by SAP
- D. ILM complements data archiving with retention management and retention warehousing.
Answer: D
NEW QUESTION 120
What options are provided by SAP Business Warehouse (SAP BW) when creating financial reports?
(Choose two.)
- A. You can display an analysis in Microsoft Access using the Business Explorer viewer.
- B. You can convert a Microsoft Excel pivot table query into an SAP BW report.
- C. You can export a Web report to a BEx Web Analyzer report.
- D. You can display an analysis on the Web using Enterprise Portal and BEx Web Analyzer.
Answer: C,D
NEW QUESTION 121
Your New GL customer uses real-time reconciliation of CO and FI. The customer wants to show the value flow of activity allocations between cost centers assigned to different profit centers. What does the customer have to configure?
There are 2 correct answers to this question.
Response:
- A. Select profit center as a characteristic for real time reconciliation between CO and FI.
- B. Define a G/L reconciliation account for direct activity allocation.
- C. Carry out a reconciliation run for activities types in the new GL.
- D. Execute the periodic transfer to profit center accounting.
Answer: A,B
NEW QUESTION 122
A customer wants to prepare and execute a global roll-out.
Which type of project within SAP Solution Manager do you recommend to start with?
- A. Template Project
- B. Maintenance Project
- C. Upgrade Project
- D. Implementation Project
Answer: A
NEW QUESTION 123
What do cost center categories allow you to do? (Choose two.)
- A. Restrict cost center planning to specific cost elements.
- B. Determine the use of cost centers in cost allocations.
- C. Restrict the assignment of specific activity types.
- D. Determine the usage of cost centers for certain methods of activity allocation.
- E. Provide default values for new cost centers (for example, block, indicators).
Answer: C,E
NEW QUESTION 124
You want to settle an internal order to cost centers, but the system does not allow you to
enter a settlement rule. What do you check?
Please choose the correct answer.
Response:
- A. Whether the sender and receiver are assigned to the same profit center
- B. Whether the costing sheet is maintained
- C. Whether the Statistical Order indicator is set
- D. Whether the PA transfer structure of the order is maintained
Answer: C
NEW QUESTION 125
A customer wants to prepare and execute a global roll-out.
Which type of project within SAP Solution Manager do you recommend to start with?
- A. Template Project
- B. Maintenance Project
- C. Upgrade Project
- D. Implementation Project
Answer: A
NEW QUESTION 126
You have completed the basic configuration of SAP Solution Manager and defined the solution landscape. Which of the following scenarios will work without further configuration steps? (Choose two)
- A. Change Request Management
- B. Early Watch Alert
- C. Business Process and Interface Monitoring
- D. Maintenance Optimizer
Answer: B,D
NEW QUESTION 127
Which SAP NetWeaver component realizes cross-system application processes?
- A. SAP Process Integration (SAP PI)
- B. SAP Enterprise Portal (SAP EP)
- C. SAP Business Warehouse (SAP BW)
- D. SAP Master Data Management (SAP MDM)
- E. SAP Exchange Infrastructure (SAP XI)
Answer: E
NEW QUESTION 128
......
SAP C_TFIN22_67 Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books |
|---|---|
| Reporting < 8% | Determine general reporting requirements for cost centers, configure cost center reporting, and create report painter reports and drill-down reports. |
| Cost Object Controlling > 12% | Determine and configure cost object controlling - planning and actuals, and customize and complete cost object controlling in a make to stock scenario and in a make to order scenario. Define WIP, results analysis, variances and revenue recognition (in cooperation with FI and SD) and configure period end closing for cost objects. |
| Profit Center Accounting 8% - 12% | Create organizational charts for profit centers, determine Profit Centers (in FI in the new GL), create Profit Centers and check master data assignments, and configure period-end closing for PCA. |
| Organizational Assignments and Process Integration < 8% | Define scopes and processes in Management Accounting, cross-company code design, sub-contracting, production execution, sales pricing, inbound freight, stock transfers, inventory valuation and transfer pricing, work in process rules and high-level requirements for organization units. Configure budgeting and availability control settings and period end closing, define statistical key figures and assign the controlling area to company codes and operating concern. Check number ranges and first integration flows with other modules (CO), and configure versions. |
| Product Cost Planning > 12% | Determine and configure product cost planning, define interface from CO-PCP (Product Cost Planning) to CO-PA (Profitability Analysis) and costing versions for alternative costings, determine cost elements structure, cost component structure, planning requirements, costing variants and multi-level costings, and carry out a Price update in the material master record. |
| Internal Orders > 12% | Distinguish between order category and order type. Determine plan data, commitments and actual requirements for internal orders and determine period-end closing activities. Define, create and configure internal orders and create a concept for internal order accounting, and customize internal order accounting, determine settlement rules and configure period-end closing for IOA. |
Authentic Best resources for C_TFIN22_67 Online Practice Exam: https://dumpstorrent.prep4surereview.com/C_TFIN22_67-latest-braindumps.html