NEW QUESTION # 157
The program manager has a global program with live component projects. The program sponsor wants the management plans, processes/procedures and technology to be uniform across the program. The requirements will create issues and result in increased costs. The program sponsor is new and has imposed these new requirements six months into a three-year program.
What should the program manager do next?
- A. Respond to the program sponsor if the program sponsor asks about It a second time
- B. Present the risks and benefits of the changes to the program sponsor
- C. Discuss the proposed changes with the stakeholders and project managers, and give the program sponsor Die best option
- D. Accept what the program sponsor requires and implement the changes
Answer: B
NEW QUESTION # 158
Which type of protection for electrical power stations provide isolation against a rise in potential of station ground and also provide drainage protection against longitudinally-induced voltages?
- A. Neutralizing transformers
- B. 2-winding neutralizing transformers
- C. Isolating transformers
- D. Unit-type neutralizing transformers
- E. Mutual drainage reactors
Answer: A
NEW QUESTION # 159
What should a program manager do to ensure that the program meets the organization's strategic goals?
- A. Assess the program reports
- B. Analyze the benefits management plan
- C. Manage the program delivery phase
- D. Engage the program steering committee
Answer: D
NEW QUESTION # 160
A program manager is responsible for constructing a USS50 million building Management suggests it will take three years to complete. The program manager can select a design-build option to optimize the construction schedule to 1 5 years However heavy demand for steel is causing price increases and delivery delays. II this trend continues, it could take as long as 4.5 years to complete construction. You learn that a new technology can yield a definitive delivery schedule of 1 25 years
What is the expected time of delivery?
- A. 1 50 years
- B. 1.25 years
- C. 175 years
- D. 1 00 years
Answer: B
NEW QUESTION # 161
An ICT distribution designer is designing a backbone cabling network that is specified for a campus network including several links approaching 2000 m (6562 It) and data rates of 100 Gb/s
What optical fiber type(s) should be used?
- A. Both OS2 and OM3 fiber
- B. OM3 fiber
- C. Both OS1 and OS2 fiber
- D. OM4 fiber
Answer: A
NEW QUESTION # 162
A large program consists of several component projects and six project managers. The program governance board requests that all components within the program undergo user acceptance testing before being released to the production environment
Where should the program manager document this?
- A. Program quality management plan
- B. Program requirements
- C. Component test plan and test cases
- D. Program governance plan
Answer: C
NEW QUESTION # 163
One of the constituent project managers asks a new program manager to obtain approval for an additional key project requirement.
A tolerance range is set, if the tolerance range is too narrow on a program what effect will multiple minor changes have on the program?
- A. Slowdown in program implementation
- B. Reduction in program risk
- C. Reduction in program quality
- D. Degradation of program communications
Answer: A
NEW QUESTION # 164
Which two of the following are ADVANTAGES of underground conduit systems? (Select two options.)
- A. Provide additional physical cable protection
- B. Require more installation time than aerial or direct-buried installations
- C. Economical over a long life
- D. Not adaptable for future facility placement or removal without disturbing the property
- E. Route planning is not as critical as aerial or direct-burial
Answer: A,C
NEW QUESTION # 165
Status information, including program and component status, cost information, risk analysis and other relevant information, is provided in which of the following?
- A. Communications log updates
- B. Information gathering and retrieval system
- C. Communications management plan
- D. Program performance report
Answer: D
NEW QUESTION # 166
What is the MAIN concern with a poke-thru installation?
- A. The diameter of the poke-thru device
- B. The fact that it is beneath the floor
- C. The compatibility with the telecommunications outlet/connector
- D. The structural integrity of the floor assembly
Answer: D
NEW QUESTION # 167
Which two of the following items should be considered for inclusion in a comprehensive working outline of a SoW? (Select two options.)
- A. Technical considerations
- B. Contract administration
- C. Schedule
- D. Financial matters
- E. Legal matters
Answer: A,D
NEW QUESTION # 168
The customer of a three-year program does not want to receive any intermediate details on the program. The program appears to be in trouble and the customer is concerned about a
new system's cost. The program manager has provided monthly performance reports throughout the program's lite cycle.
Which of the following would the customer be interested in reviewing?
- A. Estimate at completion
- B. Estimate to complete
- C. Cost performance index
- D. Original cost baseline
Answer: A
NEW QUESTION # 169
An organization must accelerate a product to market. The program manager completes the preliminary program slaps and holds a kick-off meeting Project managers submit their preliminary schedules for review
What should the program manager do next?
- A. Assign resources lo the schedule and report the revised delivery date to the project managers
- B. Integrate the project schedules into the program schedule and report the revised delivery date to the project managers
- C. Revise the project schedules to meet the program schedule and communicate to stakeholders
- D. Work with the project managers to refine the project schedules and deliverables to align with the program milestones
Answer: D
NEW QUESTION # 170
Which of the following is TRUE about convenience receptacles?
- A. They shall be connected to occupancy sensors to ensure user safety.
- B. They are those into which equipment, such as switches, shall be plugged
- C. They must be powered by emergency power to prevent loss of service.
- D. They increase the count of outlets needed on the equipment racks.
- E. They are duplex or quad receptacles mounted on perimeter walls.
Answer: E
NEW QUESTION # 171
Which of the following two items are examples of items associated with a submittal? (Select two options.)
- A. As-built
- B. Punch List
- C. Request tor permits
- D. Product Data
- E. Shop Drawings
Answer: D,E
NEW QUESTION # 172
A component is scheduled to close at the end of the week.
What should the program manager verity prior to allowing the component to close?
- A. The component has met the schedule requirements to meet program objectives
- B. The component has released resources to meet program objectives
- C. The component has met the quality requirements to meet program objectives
- D. The component has met the benefits realization criteria to meet program objectives
Answer: A
NEW QUESTION # 173
Which of the following serves as a guiding principle for a program manager when preparing a program work breakdown structure?
- A. Decompose the program work based upon available resources
- B. Decompose the program at a level sufficient to achieve control
- C. Decompose the program to the work package level
- D. Decompose the program lo the architecture baseline level
Answer: B
NEW QUESTION # 174
Several issues are identified on one component project in a program During a meeting with that component's project manager, the program manager offers several suggested resolutions Two weeks later, they meet again to review progress. The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule
What should the program manager do?
- A. Develop an immediate corrective action plan with the project manager and coach them on decision-making responsibilities
- B. Emphasize that the project manager needs to address the issues and follow up at the next scheduled meeting
- C. Join project-level issue resolution meetings to accelerate the decision-making process.
- D. Initiate discussions with the program governance board about assigning a more experienced project manager to the project
Answer: A
NEW QUESTION # 175
In a program's definition phase a program manager in country A is assigned to expand a restaurant chain into country B. communications management plan zThe program manager creates the program team by identifying the required protect management resources
Which of the following represents an initial step needed to evaluate available resources that are aligned with me program's needs''
- A. Creating a program resource management plan
- B. Completing an assessment of skills and competencies
- C. Obtaining resource availability information from the functional managers
- D. Identifying program resource requirements
Answer: D
NEW QUESTION # 176
You are designing a system requiring the transmission of data. Your system must perform higher than ________ kHz in order to do so.
- A. 0
- B. 1
- C. 2
- D. 3
- E. 4
Answer: E
NEW QUESTION # 177
A company is releasing a new product geared toward a specific geographic area. The program manager has received the program objectives and developed the program roadmap which consists of six program components Approval from the program governance board has been obtained.
What is the program manager's next step?
- A. Develop the program business case
- B. Identify the program sponsor and program stakeholders
- C. Classify the program's benefits
- D. Assign project managers and resources
Answer: B
NEW QUESTION # 178
During program execution, a program manager receives feedback from an executive sponsor (hat some program stakeholders may not understand the intended benefits of the program.
Which will provide the greatest value to clarify stakeholder perceptions?
- A. Redistributing the benefits management plan
- B. Updating the stakeholder communications requirements
- C. Redistributing the program charter
- D. Performing a stakeholder analysis
Answer: B